HowLongFor

How Long Does It Take to Remodel a Kitchen?

By the HowLongFor Editorial Team

Quick Answer

A kitchen remodel takes 6–16 weeks on average: minor refreshes take 6–8 weeks, mid-range remodels 10–12 weeks, and major gut renovations 12–16+ weeks.

Duration by Type

Minor cosmetic refresh (paint, hardware, countertops)6 weeks – 8 weeks
Mid-range remodel (new cabinets, counters, appliances, flooring)(most common)10 weeks – 12 weeks
Major renovation (layout changes, structural, custom cabinetry)12 weeks – 16 weeks
Full gut or addition (down-to-studs, room expansion)16 weeks – 20 weeks

Step-by-Step Timeline

1
Planning and design (hire pros, finalize selections, order cabinets, permits)2 weeks – 8 weeks
2
Demolition of old cabinets, countertops, flooring, and appliances2 days – 5 days
3
Rough-in work (electrical, plumbing, HVAC) plus inspection1 week – 2 weeks
4
Drywall and painting3 days – 5 days
5
Cabinet and countertop installation (template and fabrication)1 week – 2 weeks
6
Flooring and finishing touches (backsplash, fixtures, appliances)1 week – 2 weeks

Quick Answer

A typical kitchen remodel takes 6–16 weeks from demolition to completion. A minor cosmetic refresh (new paint, hardware, countertops) averages 6–8 weeks. A mid-range remodel with new cabinets, countertops, and appliances takes 10–12 weeks. A full gut renovation involving layout changes, structural work, or additions can stretch to 16–20+ weeks.

Kitchen Remodel Timeline by Scope

Project ScopeTimelineTypical Cost RangeWhat’s Included
Minor refresh6–8 weeks$10K–$25KPainting, new hardware, countertops, backsplash, minor fixture updates
Mid-range remodel10–12 weeks$25K–$60KNew cabinets, countertops, appliances, flooring, lighting, plumbing fixtures
Major renovation12–16 weeks$60K–$100K+Structural changes, layout reconfiguration, new electrical/plumbing, custom cabinetry
Full gut/addition16–20+ weeks$100K+Down-to-studs rebuild, room expansion, relocated utilities, permits

Phase-by-Phase Breakdown

1. Planning and Design (2–8 weeks before construction)

  • Hire a contractor and/or designer
  • Finalize layout, materials, and selections
  • Order cabinets (custom cabinets can take 6–12 weeks to fabricate)
  • Pull permits if required

2. Demolition (2–5 days)

  • Remove old cabinets, countertops, flooring, and appliances
  • Open walls if reconfiguring layout
  • Expect dust and noise—seal off adjacent rooms with plastic sheeting

3. Rough-In Work (1–2 weeks)

  • Electrical rewiring, adding circuits for new appliances
  • Plumbing relocation or updates
  • HVAC adjustments if needed
  • Inspection by local building authority

4. Drywall and Painting (3–5 days)

  • Patch, hang, tape, and finish drywall
  • Prime and paint walls and ceiling
  • Easier to paint before cabinets are installed

5. Cabinet and Countertop Installation (1–2 weeks)

  • Install base and wall cabinets (1–3 days for stock; up to a week for custom)
  • Template countertops after cabinet install (fabrication adds 1–2 weeks)
  • Install countertops once fabricated

6. Flooring (2–4 days)

  • Timing depends on material: tile takes longest, LVP/hardwood is faster
  • Some contractors install flooring before cabinets; others after

7. Finishing Touches (3–7 days)

  • Install backsplash
  • Mount light fixtures, outlets, and switches
  • Connect and test appliances
  • Install sink, faucet, and disposal
  • Add hardware, trim, and caulking
  • Final inspection

Factors That Affect Timeline

  • Permit requirements: Can add 2–6 weeks depending on your municipality
  • Material lead times: Custom cabinets (6–12 weeks), stone countertops (2–4 weeks), specialty tiles (4–8 weeks)
  • Contractor availability: Busy seasons (spring and summer) may delay start dates
  • Unexpected issues: Water damage, mold, outdated wiring, or asbestos can add 1–4 weeks
  • Decision delays: Changing materials or design mid-project is the #1 cause of timeline overruns
  • Supply chain disruptions: Material shortages can push timelines by weeks

Tips to Keep Your Remodel on Track

  1. Finalize all selections before demolition—cabinets, counters, appliances, fixtures, tile, paint colors
  2. Order long-lead items early, especially custom cabinets and specialty materials
  3. Set up a temporary kitchen with a microwave, mini-fridge, and coffee maker
  4. Build in a 2–3 week buffer for unexpected delays
  5. Communicate weekly with your contractor—address issues before they snowball
  6. Avoid making changes once construction starts unless absolutely necessary

Estimated Cost

$10,000$100,000

Ranges from a minor refresh (~$10K-$25K) to a full gut renovation ($100K+); mid-range remodels average $25K-$60K.

Minor refresh$17,500
Mid-range remodel$42,500
Major renovation$80,000

Sources

Related Questions

How long did it take you?

week(s)

Was this article helpful?